In Irkutsk on Bogdanov Lane, preparatory work has begun for construction of a kindergarten for 100 children. Contractor Novo-Stroy LLC must set up fencing, a site camp, and start excavation, with completion planned for September 2014. The new two story kindergarten, costing 103.8 million rubles, will have five groups, a sports and music hall, an art studio, and other needed rooms.
Preparatory work at the site in Bogdanov Lane in the Pravoberezhny District is being carried out by Novo-Stroy LLC. Within a week, the contractor must install a barrier, set up a temporary construction camp, relocate utilities, and begin excavation work. According to the contract, construction must be completed in September 2014. The cost of the kindergarten for 100 children will amount to 103.8 million rubles.As reported by the Irkutsk Capital Construction Department, it will be a two-story building with a basement area of 2,647.9 square meters, and the landscaping area will be 2,729.5 square meters. The project provides for five groups: nursery, younger, middle, older, and preparatory. The building will also house medical, food service, and utility units, a multipurpose hall for sports and music classes, a classroom for preparatory lessons, and an art studio.
As a reminder, as part of the implementation of the long-term targeted program “Construction of Social Infrastructure Facilities for 2013–2017,” it is planned to build 4 kindergartens in 2014: on Novatorov Street, Rosa Luxemburg Street, Sevastopolskaya Street, and Bogdanov Lane, which will make it possible to create 770 new places.