In Irkutsk, a new bridge over the channel on Youth Island is being built, retaining walls are already installed, and a new surface is being used. Construction is planned to finish by August 30, after which the surrounding area will be improved. For now, a temporary crossing is in use for traffic, while IrkutskAvtodor and the youth council are repairing the pedestrian bridge.

In Irkutsk, the bridge maintenance service will build a new bridge across the channel on Yunost Island. Retaining walls have already been installed, and a new surface is being used in the work.
They plan to complete construction by August 30. Work will also be carried out to improve the surrounding area. In the meantime, a temporary crossing for vehicles will operate on Yunost, which is currently being installed. When the bridge opens, the temporary crossing will be removed, the Irkutsk city administration press service reports.
In addition, the municipal enterprise “IrkutskAvtodor,” together with the youth council, is carrying out repairs on the pedestrian bridge.